Example of Anticipated Contract Loss
|
|||
Material Issued
|
|
|
50,000
|
Labour
|
|
|
40,000
|
Plant value Begning
|
|
|
100,000
|
Ovehreads
|
|
|
40,000
|
Matrial at Site
|
|
|
5,000
|
Plant at Closing
|
|
|
80,000
|
Toal estimated Cost
|
|
|
230,000
|
Contract Price
|
|
|
190,000
|
Work Certified
|
|
|
120,000
|
Solution
|
|||
Contract Cost Profit & Loss
|
|||
Work Certified
|
|
|
120,000
|
Material Used
|
(50,000-5000)
|
45,000
|
|
Labour
|
40,000
|
||
Plant value Begning
|
(100,000-80,000)
|
20,000
|
|
Ovehreads
|
40,000
|
||
Less: Cost of Good Sold
|
|
145,000
|
|
Loss for the year
|
|
|
(25,000)
|
Total Loss
|
|||
Loss for the year
|
(25,000)
|
||
Future Loss
|
(15,000)
|
||
Total Loss
|
(230,000-190,000)
|
|
(40,000)
|