Tuesday 30 October 2012

Example of anticipated Contract Loss





Example of Anticipated Contract Loss
Material Issued


           50,000
Labour


           40,000
Plant value Begning


         100,000
Ovehreads


           40,000
Matrial at Site


             5,000
Plant at Closing


           80,000
Toal estimated Cost


         230,000
Contract Price


         190,000
Work Certified


         120,000
Solution
Contract Cost Profit & Loss
Work Certified


120,000
Material Used
(50,000-5000)
           45,000
Labour
           40,000
Plant value Begning
(100,000-80,000)
           20,000
Ovehreads
           40,000
Less: Cost of Good Sold

         145,000
Loss for the year


         (25,000)
Total Loss
Loss for the year
         (25,000)
Future Loss
         (15,000)
Total Loss
(230,000-190,000)

         (40,000)